Project MateProject Management Essentials Terms & Definitions
Every definition you need to communicate with confidence on any project. Understand the language of project management with clear, practical definitions.
All 55Frameworks & Structure 10Earned Value Management 12Scheduling 9Risk & Change 7Site & Commercial 17
Frameworks & Structure10 TERMS
RAIDRisks, Assumptions, Issues, Dependencies
A single log that captures the four things most likely to derail a project before they do: Risks (might happen), Assumptions (believed true but unverified), Issues (already happening), and Dependencies (work relying on something outside your control). Reviewed weekly, it catches problems while they're still cheap to fix.
RACIResponsible, Accountable, Consulted, Informed
A matrix mapping every task or decision against the people involved, with exactly one Accountable owner per row. Prevents the two failure modes of team communication: work nobody owns, and decisions everybody thinks they own.
WBSWork Breakdown Structure
The project's scope broken into smaller pieces until each is small enough to assign, estimate, and measure. If a WBS line can't carry a number — quantity, duration, cost — it needs breaking down further.
OBSOrganization Breakdown Structure
The project's people and companies arranged by role and reporting line — who reports to whom, which subcontractor owns which package. Overlaid on the WBS, it answers who is accountable for each piece of work.
RBSRisk Breakdown Structure
Risks grouped by source — technical, external, organizational, project management — instead of listed randomly. Grouping surfaces patterns a flat list hides.
SWOTStrengths, Weaknesses, Opportunities, Threats
A four-box exercise for sizing up a position — a bid decision, a project at kickoff, a new market. Strengths and weaknesses look inward; opportunities and threats look outward.
PMOProject Management Office
The team or function that sets how projects are run across an organization — templates, reporting standards, governance — so quality doesn't depend on which PM you happened to get.
PMBOKProject Management Body of Knowledge
PMI's reference guide describing standard processes and terminology across the profession. Useful as a common language — not a rulebook to follow literally on every project.
CharterProject Charter
The document that formally authorizes a project to exist — states its purpose, high-level scope, and the PM's authority to spend budget and direct resources.
Triple ConstraintIron Triangle
The three variables that trade off on every project: scope, time, and cost — quality is often added as a fourth. Push one and at least one other moves.
Earned Value Management12 TERMS
EVMEarned Value Management
A method comparing what was planned, what was actually built, and what it cost — in the same currency — to measure schedule and cost performance independently. See PV, EV, AC and the metrics derived from them, below.
PVPlanned Value
The value of work the schedule says should be complete by today, in contract money. Also called BCWS.
PV = % planned × budgetEVEarned Value
The value of work actually completed by today, priced at contract rates — not what was spent, what was built. Also called BCWP.
EV = % complete × budgetACActual Cost
What it actually cost to produce the earned value — wages, materials, equipment, everything spent. Also called ACWP.
SVSchedule Variance
Zero is on schedule, negative is behind, positive is ahead. Measured in money rather than days — see SPI for the ratio form.
SV = EV − PVCVCost Variance
Positive means the work cost less than its earned value — under budget. Negative means over budget.
CV = EV − ACSPISchedule Performance Index
Above 1.0 is ahead of schedule, below 1.0 is behind. An SPI of 0.91 means 91 fils of scheduled work delivered for every riyal the plan expected.
SPI = EV ÷ PVCPICost Performance Index
Above 1.0 means every riyal spent produces more than a riyal of earned value. Widely considered the strongest single predictor of final cost overrun.
CPI = EV ÷ ACEACEstimate At Completion
The forecast total cost of the project if current cost performance continues. Several formulas exist; this is the simplest and most used.
EAC = Budget ÷ CPIETCEstimate To Complete
How much more money is expected to be needed to finish the project from today.
ETC = EAC − ACVACVariance At Completion
The forecast overrun or underrun at completion, in money. Negative means the project is heading over budget.
VAC = Budget − EACTCPITo-Complete Performance Index
The cost efficiency the remaining work must achieve to finish on the original budget. Far above the CPI achieved so far is a sign the budget is no longer realistic.
TCPI = (Budget−EV) ÷ (Budget−AC)Scheduling9 TERMS
CPMCritical Path Method
The sequence of dependent tasks that determines the shortest possible project duration — any delay on it delays the whole project. Everything else has float.
FloatTotal Float / Free Float
The time an activity can slip without delaying the project (total float) or the next activity (free float). Zero float means the activity is on the critical path.
S-Curve
A cumulative progress chart that naturally forms an S-shape over time. Plotting planned and actual value on the same chart makes delay visible at a glance.
Baseline
The original approved version of the schedule, budget, or scope, frozen as a reference point. Progress is measured against it, not against last month's report.
Milestone
A zero-duration marker for a significant point in the project — design freeze, first pour, practical completion. It carries no work of its own.
Look-ahead Schedule
A short rolling window — typically two to three weeks — pulled from the master programme and reviewed weekly for what's coming and what could block it.
Fast-tracking
Overlapping activities originally planned sequentially, to shorten the schedule. Faster, but increases rework risk.
Crashing
Adding resources to a critical-path activity to shorten its duration. Costs more per day saved than the original plan; used when the deadline outweighs the budget.
Resource Leveling
Adjusting a schedule to smooth resource demand rather than swinging from 40 electricians one week to 8 the next — usually extends the schedule slightly in exchange for a deployable workforce.
Risk & Change7 TERMS
Risk Register
A log of identified risks, each scored by likelihood and impact, with an assigned response and owner. Only useful if reviewed on a fixed rhythm.
Contingency
Budget or time set aside for known-unknowns — risks already identified but not yet certain to land. Different from management reserve, which covers unknown-unknowns.
Change Order / VOVariation Order
A formally instructed and priced change to the contracted scope — the document that turns "the client asked for an extra" into something invoiceable.
Scope Creep
Small, unrecorded additions to scope that accumulate without a corresponding change in budget or schedule — usually because nobody raised a formal change request.
Force Majeure
Contractually defined events outside either party's control — extreme weather, war, government action — that can excuse delay without penalty, as defined in the specific clause.
Escalation
Raising an issue to a higher level of authority when it can't be resolved at the level where it was found — a defined path, not a last resort out of frustration.
Stakeholder
Anyone who can affect, or is affected by, the project's outcome. Managing stakeholders well means understanding their interest and influence before you need something from them.
Site & Commercial17 TERMS
BOQBill of Quantities
An itemized list of the works, with measured quantities and unit rates, forming the commercial backbone of most construction contracts.
ITPInspection & Test Plan
Maps each construction activity to its required inspections, hold points, and acceptance criteria — agreed with the consultant before anyone argues about what "passed" means.
NCRNon-Conformance Report
A formal record raised when completed work doesn't meet the specification — what was found, where, and the corrective action required before acceptance.
RFIRequest for Information
A formal question to the designer when drawings or specifications don't give enough information to proceed — with a due date, since unanswered RFIs are a common cause of avoidable delay.
EOTExtension of Time
A contractual claim for additional time, usually for an employer-caused or excusable delay, that moves the completion date without automatically implying additional cost.
DLPDefects Liability Period
The period after handover — commonly 12 months — during which the contractor remains responsible for fixing defects at their own cost. Also called the warranty period.
LDLiquidated Damages
A pre-agreed daily or weekly deduction for late completion, stated in the contract so both sides know the cost of delay in advance.
Retention
A percentage of each payment certificate withheld as security against defects — commonly 5–10% — released partly at handover and partly at the end of the DLP.
Punch ListSnag List
Minor defects and incomplete items identified at practical completion that must be closed out before final handover.
Method Statement
A step-by-step document describing how an activity will be carried out safely and to specification — sequence, equipment, manpower, controls — submitted for approval before work starts.
MOMMinutes of Meeting
The written record of what was discussed, decided, and assigned — issued promptly and treated as the official version unless formally disputed.
Submittal
Material samples, shop drawings, or product data submitted for approval before procurement or installation — tracked by revision code (A, B, C) until approved.
QA/QCQuality Assurance / Quality Control
QA prevents defects through procedures and ITPs; QC inspects and catches them if they happen anyway. One is proactive, the other a safety net.
HSEHealth, Safety & Environment
The function covering worker safety, environmental compliance, and incident prevention on site — measured, among other things, by the LTI rate.
Value Engineering
A structured review of a design to reduce cost or improve constructability without reducing function or quality — deliberate and early, unlike cutting corners under pressure later.
JVJoint Venture
Two or more companies combining resources and sharing risk and profit under a separate agreement — usually because the project needs a scale neither company has alone.
Kickoff Meeting
The first formal meeting of a project team after award, aligning everyone on scope, roles, communication protocols, and early milestones.
Missing a term you use on site? Suggest it — the dictionary grows from real requests, same as the template library. Want the metrics in action? Read Earned Value, Explained Like You’re on Site.